Friday, February 17, 2006

Waiting for the City


The long wait continues for the city of Fort Lauderdale to approve minor changes to the plumbing layout. The revisions have been in for review for 8 days now and no end in sight. The plumbing cannot be inspected until the review is done.

Monday, February 13, 2006

Plumbing progress


The rough plumbing is in place and awaiting Building Dept approval of the drawing changes before inspection can take place. The building dept is currently at one week without approval.

Wednesday, February 08, 2006


Our Casa Bella I project is successfully out of the ground. The ground has been compacted, footers poured and the soil compacted again. The next phase is the slab but before that can be poured the architect must stamp a change to the plumbing isometric, get it approved by the city, the plumber can then run the underground pipes. In addition the electrician, compaction, soil test and termite treatment are required