The inspections are all passed and the final tile set is going down. They are being applied with foam which gives superior adhesion and much less penetration of the membrane.
The stucco and the foam trim are almost done. The 3rd floor sheathing has been stuck in the city approval process for a while but should be ready for stucco work by weeks end.
The framing is completed enough for the plumbers and electricians to make progress. The window bucks are installed and passed inspection. The windows are in town and after a few more adjustments to the bucks, are ready to be installed. The trusses and roof sheathing are on, waiting inspection.
The last rows of blocks for the parting wall are up and the final forming for the cap beams will start next week. The metal stud wall is close to finished.