Wednesday, May 17, 2006

The second floor is poured



In spite of a driving rain in the afternoon we were able to get the entire pour finished

Monday, May 08, 2006

Inspection partially passes and work proceeds


The forming and metal work was satisfactory to the inspector but a new, unannounced requirement to have a spot survey reviewed through the city before the inspection can pass. That is processing while we go ahead and close up the forms ready for the pour. This will be an extensive pour, 90+ cubic yards of concrete doing the columns, tie beams, second floor slab and stairs all at once. We are hoping for Thursday