Wednesday, March 29, 2006

Slab is poured



The slab pour went smoothly and looks good. The blocks should start going up by the weekend.

Thursday, March 16, 2006

Ready for Inspection



The compaction, pest control, plastic, wire mesh and the extra footers for the elevators are done and waiting inspection on Friday.

Tuesday, March 07, 2006

Ready for forming the slab


The plumbing and electrical work undergrade is done and inspected. The next step is final leveling and compacting. Then termite protection, plastic and mesh to get ready for slab inspection.